Electricity prices and what power costs to make
What Virginia homes pay for electricity, how that has changed, and what different power sources cost to build and run. Every number links to its source, and each dataset can be downloaded.
How home electricity prices have changed
Average price Virginia homes paid per kilowatt-hour, compared with the U.S. average, 1990 to 2026. Not adjusted for inflation.
Show the numbers and sources
Average revenue per kilowatt-hour sold to homes by all providers (EIA-861 / EIA-826): total residential revenue divided by residential kWh sold, including taxes passed through on bills only where utilities report them as revenue. Not adjusted for inflation. 2026 covers January to September only, so it is not directly comparable with full years (summer months are usually priced higher). For comparison, January to September 2025 was 15.14 cents in Virginia and 17.14 cents nationally.
Dominion's typical monthly bill
What a Dominion Energy Virginia home using 1,000 kWh a month pays, including base rates, fuel and riders.
Show the numbers and sources
| Date | Typical bill (1,000 kWh) | Source |
|---|---|---|
| Jul 2026 | $180.79 | York County Dominion update Aug 2026 |
| Jan 2026 | $170.61 (approx.) | York County Dominion update Aug 2026 (chart) |
| Sep 2025 | $159.57 | WTVR 2026-09-03 / RD716 p.9 (Oct 2025) |
| Jul 2025 | $149.92 | SCC status report 2025 (RD716) p.6 |
| Jul 2024 | $133.74 | SCC status report 2024 (RD717) p.7 |
| Jul 2023 | $125.12 | SCC status report 2023 (RD572) p.7 |
| Jul 2022 | $136.93 | SCC status report 2022 (RD418) p.9 |
| Jul 2021 | $121.28 | SCC status report 2021 (RD390) p.5 |
| Jul 2020 | $116.69 | SCC status report 2020 (RD282) p.4 |
| Jul 2019 | $113.76 | SCC status report 2019 (RD320) p.2 |
| Jul 2018 | $115.00 | SCC status report 2018 (RD274) p.4 |
| Jul 2015 | $109.40 (approx.) | SCC status report 2019 (RD320) p.2 chart |
| Jul 2007 | $90.59 | SCC VEURA status report 2018 (RD274) p.4 |
A typical bill for a home using 1,000 kWh in a month, as Dominion and the SCC report it, including base rates, fuel and riders. Snapshots are mostly July 1 of each year; there is a gap between 2007 and 2015. Values marked approximate were read from a chart. SCC status reports are published on the General Assembly's Reports and Documents site.
Prices have risen faster than the cost of making power
What Virginia homes pay per kWh, compared with what electricity costs on the regional wholesale market and what it costs to run Virginia's power plants. All in cents per kWh, not adjusted for inflation.
In 2025, Virginia homes paid 15.28¢ per kWh on average. Power itself cost about 6.20¢ on the regional wholesale market and regional transmission about 2.03¢. The remaining 7.0¢ pays for local power lines and poles, the utility's own costs above market prices (such as paying off plants it built), state-mandated programs and riders, power lost on the lines, taxes and the utility's profit.
Where Virginia's in-state power comes from
Share of electricity made in Virginia, by source. Virginia also buys a large share of its power from the rest of PJM.
2005: Coal 44.1%, Natural gas 10.3%, Nuclear 34.7%, Solar and wind 0%, Other (hydro, wood, oil, biomass) 11%. 2010: Coal 34.2%, Natural gas 22.8%, Nuclear 35.7%, Solar and wind 0%, Other (hydro, wood, oil, biomass) 7.5%. 2015: Coal 20.2%, Natural gas 39%, Nuclear 32.8%, Solar and wind 0%, Other (hydro, wood, oil, biomass) 8.1%. 2020: Coal 3.7%, Natural gas 60.2%, Nuclear 28.9%, Solar and wind 1.3%, Other (hydro, wood, oil, biomass) 6%. 2024: Coal 1.9%, Natural gas 58.6%, Nuclear 27.8%, Solar and wind 6.7%, Other (hydro, wood, oil, biomass) 5.1%
Show the numbers, sources and caveats
| Year | Virginia home price (¢/kWh) | Wholesale power (¢/kWh) | Transmission and grid fees (¢/kWh) | Virginia plants' fuel and upkeep (¢/kWh) |
|---|---|---|---|---|
| 2026 (partial) | 17.03 | 9.01 | 2.15 | – |
| 2025 | 15.28 | 6.20 | 2.03 | – |
| 2024 | 14.41 | 3.62 | 1.93 | 2.48 |
| 2023 | 14.26 | 3.50 | 1.80 | 2.67 |
| 2022 | 13.34 | 8.32 | 1.67 | 4.51 |
| 2021 | 11.96 | 5.01 | 1.58 | 3.01 |
| 2020 | 12.03 | 3.02 | 1.49 | 2.36 |
| 2019 | 12.07 | 3.80 | 1.31 | 2.84 |
| 2018 | 11.73 | 5.08 | 1.22 | 3.37 |
| 2017 | 11.55 | 4.25 | 1.22 | 3.00 |
| 2016 | 11.36 | 4.05 | 1.09 | 2.95 |
| 2015 | 11.37 | 4.85 | 1.02 | 3.30 |
| 2014 | 11.10 | – | – | – |
| 2013 | 10.84 | 4.65 | 0.80 | – |
| 2012 | 11.08 | 4.18 | 0.71 | – |
| 2011 | 10.64 | 5.63 | 0.65 | – |
| 2010 | 10.45 | 5.84 | 0.59 | – |
| 2009 | 10.61 | 4.76 | 0.55 | – |
| 2008 | 9.62 | 7.57 | 0.55 | – |
| 2007 | 8.74 | 6.16 | 0.54 | – |
| 2006 | 8.49 | 5.13 | 0.51 | – |
| 2005 | 8.16 | 6.39 | 0.53 | – |
| Year | Coal (%) | Natural gas (%) | Nuclear (%) | Solar and wind (%) | Other (hydro, wood, oil, biomass) (%) |
|---|---|---|---|---|---|
| 2005 | 44.1 | 10.3 | 34.7 | 0.0 | 11.0 |
| 2010 | 34.2 | 22.8 | 35.7 | 0.0 | 7.5 |
| 2015 | 20.2 | 39.0 | 32.8 | 0.0 | 8.1 |
| 2020 | 3.7 | 60.2 | 28.9 | 1.3 | 6.0 |
| 2024 | 1.9 | 58.6 | 27.8 | 6.7 | 5.1 |
- Wholesale figures are averages for all of PJM, the regional grid Virginia belongs to, not Dominion's area alone. They are measured where power enters local lines, before local losses.
- Dominion owns most of the plants that serve its customers and recovers their cost, including building them, through base rates and riders set by the SCC. The wholesale price shows what that power is worth on the market, not what Dominion actually spends.
- 2026 covers January to September for home prices and January to October for wholesale costs.
- Left out: the monitor's 2014 monthly table shows an energy cost of $93.20/MWh, far above the $53.14/MWh average energy price in its own 2014 State of the Market report, so that year's table looks inconsistent. Source: Monitoring Analytics, 2014 State of the Market Report for PJM (press release, March 2015).
- How the Virginia plant figure is built: For each year: fuel cost per MWh = Virginia delivered fuel price ($/MMBtu, EIA Table 6) x U.S. average heat rate for that fuel (EIA Table 8.1); nuclear fuel and all operation and maintenance costs use U.S. investor-owned utility averages (EIA Table 8.4: fossil steam for coal and oil, gas turbine and small scale for gas, solar and wind). Hydro, solar and wind have no fuel cost. Weighted by each source's Virginia generation (EIA Table 5). Wood, other biomass and other sources (about 3% of generation) are left out because no comparable cost is published; pumped storage and batteries are left out because they store power rather than make it. Building costs are not included.
- Virginia also imports a large share of its power from the rest of PJM: in 2024, retail sales were 138 million MWh and in-state generation was 103 million MWh (EIA).
Sources: Monitoring Analytics (PJM's Independent Market Monitor), Components of the Total Cost of PJM Wholesale Power, monthly tables 2005 to 2026 (2026 through October), annual figures weighted by monthly real-time load; U.S. Energy Information Administration, State Electricity Profiles 2024, Virginia, Table 5 (generation by source) and Table 6 (delivered fuel prices); U.S. Energy Information Administration, Electric Power Annual 2025, Table 8.1 (average operating heat rates); U.S. Energy Information Administration, Electric Power Annual 2025, Table 8.4 (operating expenses of major investor-owned utilities, from FERC Form 1); home prices from the EIA sources listed with the chart above.
What it costs to make electricity, by source
Cost per megawatt-hour over a plant's life, before tax credits. Bars show Lazard's low to high estimate. $100 per MWh is 10 cents per kWh.
Building a new power plant
- Onshore wind$37–$99
- Large solar farm$40–$98
- Onshore wind + battery$49–$140
- Gas plant, combined cycle (runs most hours)$51–$129
- Large solar farm + battery$61–$156
- Geothermal$67–$111
- Coal plant$72–$177
- Community and business rooftop solar$88–$197
- Offshore wind · CVOW estimate $84CVOW $84$105–$167
- Gas peaker plant (runs only at peak times)$144–$276
- New nuclear plant$175–$255
Running an existing plant that is already paid off
- Existing nuclear plant (paid off)$26–$36
- Existing gas combined-cycle plant (paid off)$32–$51
- Existing coal plant (paid off)$34–$69
Storing power in a large battery
- Large battery, 4-hour$210–$292
- Large battery, 2-hour$215–$414
Show the numbers and sources
| Source of power | Low ($/MWh) | High ($/MWh) | Cents per kWh | Source |
|---|---|---|---|---|
| Onshore wind | $37 | $99 | 3.7–9.9¢ | Lazard, Levelized Cost of Energy+ (LCOE v19.0, LCOS v11.0), July 2026, p. 7 |
| Large solar farm | $40 | $98 | 4.0–9.8¢ | Lazard, Levelized Cost of Energy+ (LCOE v19.0, LCOS v11.0), July 2026, p. 7 |
| Onshore wind + battery | $49 | $140 | 4.9–14.0¢ | Lazard, Levelized Cost of Energy+ (LCOE v19.0, LCOS v11.0), July 2026, p. 7 |
| Gas plant, combined cycle (runs most hours) | $51 | $129 | 5.1–12.9¢ | Lazard, Levelized Cost of Energy+ (LCOE v19.0, LCOS v11.0), July 2026, p. 7 |
| Large solar farm + battery | $61 | $156 | 6.1–15.6¢ | Lazard, Levelized Cost of Energy+ (LCOE v19.0, LCOS v11.0), July 2026, p. 7 |
| Geothermal Lazard marks this as illustrative: an older estimate adjusted for inflation. | $67 | $111 | 6.7–11.1¢ | Lazard, Levelized Cost of Energy+ (LCOE v19.0, LCOS v11.0), July 2026, p. 7 |
| Coal plant Excludes the cost of shipping and storing coal. | $72 | $177 | 7.2–17.7¢ | Lazard, Levelized Cost of Energy+ (LCOE v19.0, LCOS v11.0), July 2026, p. 7 |
| Community and business rooftop solar | $88 | $197 | 8.8–19.7¢ | Lazard, Levelized Cost of Energy+ (LCOE v19.0, LCOS v11.0), July 2026, p. 7 |
| Offshore wind | $105 | $167 | 10.5–16.7¢ | Lazard, Levelized Cost of Energy+ (LCOE v19.0, LCOS v11.0), July 2026, p. 7 |
| Gas peaker plant (runs only at peak times) | $144 | $276 | 14.4–27.6¢ | Lazard, Levelized Cost of Energy+ (LCOE v19.0, LCOS v11.0), July 2026, p. 7 |
| New nuclear plant | $175 | $255 | 17.5–25.5¢ | Lazard, Levelized Cost of Energy+ (LCOE v19.0, LCOS v11.0), July 2026, p. 7 |
| Existing nuclear plant (paid off) Marginal cost to keep running an existing, fully paid-off plant, including decommissioning. | $26 | $36 | 2.6–3.6¢ | Lazard, Levelized Cost of Energy+ (LCOE v19.0, LCOS v11.0), July 2026, p. 12 |
| Existing gas combined-cycle plant (paid off) Marginal cost to keep running an existing, fully paid-off plant. Rises and falls with gas prices. | $32 | $51 | 3.2–5.1¢ | Lazard, Levelized Cost of Energy+ (LCOE v19.0, LCOS v11.0), July 2026, p. 12 |
| Existing coal plant (paid off) Marginal cost to keep running an existing, fully paid-off plant. | $34 | $69 | 3.4–6.9¢ | Lazard, Levelized Cost of Energy+ (LCOE v19.0, LCOS v11.0), July 2026, p. 12 |
| Large battery, 4-hour Cost per MWh the battery delivers, including the power used to charge it. Not directly comparable with generators. | $210 | $292 | 21.0–29.2¢ | Lazard, Levelized Cost of Energy+ (LCOE v19.0, LCOS v11.0), July 2026, LCOS section |
| Large battery, 2-hour Cost per MWh the battery delivers, including the power used to charge it. Not directly comparable with generators. | $215 | $414 | 21.5–41.4¢ | Lazard, Levelized Cost of Energy+ (LCOE v19.0, LCOS v11.0), July 2026, LCOS section |
| Dominion's Coastal Virginia Offshore Wind (CVOW) Dominion's own estimate (May 2026), within the $80 to $90 range in its 2021 SCC filing. Dominion later raised CVOW's total cost estimate to about $11.7 billion (Utility Dive, July 31, 2026); it has not been shown how that changes this figure. | $84 (single estimate) | 8.4¢ | Utility Dive, "Dominion upbeat on offshore wind as cost estimate eases, sales rise", May 4, 2026 (Dominion's first-quarter 2026 earnings call) | |
Levelized cost of energy (LCOE): the average cost of each megawatt-hour over a plant's life, covering building, financing, fuel and upkeep, with no federal tax credits. Ranges reflect different sites, sizes and financing. These are national estimates for a new plant, not Virginia bills: they leave out transmission, grid upgrades and backup needs. 1 MWh = 1,000 kWh, so $100/MWh is 10 cents per kWh. Home rooftop solar, home batteries and plug-in (balcony) solar: the 2026 Lazard report no longer includes a home-scale case, and we have not found a comparable, sourced 2026 figure yet.
How to read these together
Your bill pays for much more than making electricity. It also covers power lines, poles and substations, programs the law requires, and the utility's profit, so a cheap power source does not translate one-for-one into a cheaper bill. The cost chart compares sources on the same footing: the average cost per megawatt-hour of power over a plant's life.
The cost of making power from a new plant also depends on where and how it is built, on interest rates, and, for gas and coal, on fuel prices, which can swing from year to year. Plants that are already paid off cost much less to keep running, which is why the chart shows them separately.
Utility rate cases at the State Corporation Commission decide which of these costs end up on your bill. See the cases we track and their comment deadlines.